Himachal Gets Hydel Power Arrears In Energy Over 20 Years, Not Cash : Supreme Court

Reported By: admin • November 11, 2026, 9:58 am
0:00 / --:--
1x

Himachal Gets Hydel Power Arrears In Energy

Over 20 Years, Not Cash : Supreme Court


Case: State of Himachal Pradesh v. Union of India & Others (Original Suit No. 2 of 1996) – Judgment

Court: Supreme Court of India (Original Jurisdiction, Article 131)

Citation: 2026 INSC 1200

Coram: Chief Justice Surya Kant, Justice Joymalya Bagchi and Justice V. Mohana (Judgment by the Chief Justice)

Date of Judgment: 6 November 2026

HEADNOTE

Keywords: Constitution of India, Article 131 – Original Suit – Punjab Reorganisation Act, 1966, Section 78 – Bhakra-Nangal and Beas Projects – Share in Hydel Power – Energy Arrears – Capital Cost – Cashless Settlement – Execution of Decree – Decree dated 27.09.2011

  1. Execution, not re-litigation: The present exercise is in the nature of execution proceedings. It does not reopen what the decree of 27.09.2011 decided, nor allow parties to re-agitate settled issues.
  2. Energy arrears fixed: The arrears due to Himachal Pradesh, as computed by the Union of India, are taken at 13,066 million units (MU), to be supplied by Punjab and Haryana in the ratio of 58:42 for Bhakra-Nangal and 60:40 for Beas.
  3. Cashless adjustment of capital cost: Himachal’s liability for its 7.19% share of capital cost, assessed at Rs. 420.77 crores, is adjusted against the energy at Rs. 3.85 per unit, about 1,093 MU. The balance of about 11,973 MU is to be supplied in kind.
  4. Longer period as a concession: To ease the burden on the defendant States, the period for supplying the arrears is raised from 15 years to 20 years, at about 598 MU a year for the balance.
  5. Old arrears cannot be valued at today’s rate: Converting the capital cost at the current O&M rate inflates the liability and is misleading, because the arrears relate to an earlier period.
  6. Binding directions: The directions are binding and must be acted on without reservation. The expectation of a decree pending for decades cannot be made fruitless by a recalcitrant judgment debtor.

BRIEF FACTS

Himachal Pradesh filed this original suit in 1996 under Article 131 claiming a share in the power from the Bhakra-Nangal and Beas Hydel Projects, which were built largely on its territory, against the Union of India, Punjab, Haryana, Rajasthan and Chandigarh. By judgment dated 27.09.2011, the Supreme Court held that Himachal was entitled to 7.19% of the power attributable to composite Punjab. This works out to 6.095% of the Bhakra-Nangal Project, 5.752% of Beas Unit I and 2.984% of Beas Unit II. The Union of India was directed to compute the amounts due.

The Union of India computed the shortfall at 13,066 million units (affidavit of 05.07.2013). Punjab and Haryana disputed the computation, and settlement efforts through the Attorney General between 2014 and 2025 did not succeed. The Attorney General then proposed a cashless framework: arrears supplied in kind over lean seasons (October to March), with Himachal’s capital-cost liability adjusted against the energy. Himachal and Haryana agreed in principle on 30.07.2026 and 20.08.2026. Punjab objected that (i) the 1.2 lakh units a day supplied to Himachal had not been deducted, (ii) the capital cost should be converted at the O&M rate of 79 paise a unit, and (iii) the arrears should be spread over 30 years.

KEY FINDINGS OF THE COURT

Note: The findings highlighted in yellow are the main findings of the Court most relied upon for the judgment.

  1. Punjab’s objections were vague attempts to re-argue a settled decree. The Court said the exercise is in the nature of execution and does not reopen the decree of 27.09.2011. The Union of India’s computation had been substantially accepted by all, and it was not the product of a single method. Punjab’s contentions were vague and superficial. The 1.2 lakh units a day had already been accounted for in the capital-cost adjustment, and valuing old arrears at today’s O&M rate was inaccurate and misleading (paras 30–36).
  2. Capital cost is adjusted against the energy; the rest is supplied in kind. Himachal’s capital-cost liability is Rs. 420.77 crores (Rs. 249.23 crores for Punjab and Rs. 171.55 crores for Haryana), representing the unreimbursed share of loan servicing since 1966-67. It is adjusted at Rs. 3.85 per unit against about 1,093 MU of the 13,066 MU arrears. Himachal pays the BBMB charges for the year in which each tranche is received. The settlement is on a cashless basis (para 41(a)–(f)).
  3. The supply period is 20 years, not 15 or 30. The only ground Punjab gave for 30 years was an earlier written submission of the Union of India, and Haryana accepted 15 years. The Court extended the period from 15 to 20 years as a concession to the defendant States, so the balance of about 11,973 MU is to be supplied at about 598 MU a year over 20 lean seasons (paras 37–38, 41(e)).
  4. Punjab accepted the method in principle. Although Punjab disputed the final dues, it accepted in principle the method used to work out Himachal’s capital-cost liability (para 39).
  5. Settlement efforts and compliance. The Court recorded its appreciation of the sustained efforts of the Attorney General to mediate and frame the settlement, and warned that its directions must be acted on without reservation (paras 42–43).
  6. Court’s clarification on the decree. The Court noted that the decree’s clause (iii) refers to amounts due from Defendant Nos. 3 and 4, which is inconsistent with the rest of the decree, and that later proceedings treated Punjab and Haryana (Defendant Nos. 2 and 3) as the judgment debtors (para 5.26).

RESULT

Directions issued and suit disposed of. Punjab and Haryana must supply 13,066 MU of arrears over 20 lean seasons (653 MU a year before adjustment) in the ratio of 58:42 and 60:40. Himachal’s Rs. 420.77 crores capital-cost liability is adjusted at Rs. 3.85 per unit, leaving about 11,973 MU at about 598 MU a year, on a cashless basis. The suit and pending applications stand disposed of (paras 41–45).

Case Title: State of Himachal Pradesh v. Union of India & Others

Citation: 2026 INSC 1200

Appearance: The learned Attorney General for India appeared for the Union of India. Other counsel are not named in the judgment.

State of Himachal Pradesh v. Union of India

📄 Open / Download Judgment PDF

On iPhone or iPad, choose “Save to Files” in the share sheet. If the PDF opens in Safari, tap Safari’s Share icon, then “Save to Files.”

Leave a Reply

Your email address will not be published. Required fields are marked *

For full act and section text, search the Bare Acts Library.

Account Access

Forgot your password? | Register